The Challenge

To provide our customer, a custom wooden structure and joinery fabricator, with a system that would improve production times and allow them to move large pieces of material safety and more efficiently.

Special Consideration

The company’s production is located in a very unique and stunning facility made completely out of wood. They needed the ability to load large pieces into milling machines and move finished products throughout the building.  Crane-Tec was challenged with designing a structural system that worked within their wooden building framework.

Our Team Approach

Crane-Tec worked closely with the customer to learn their specific needs and expectations of the new system. With our combined efforts, and after reviewing several options, solutions included:


Two 2.5 Ton top running single girder cranes.


Radio control operation for each crane, with the option to operate each crane individually, or in tandem. This feature allows the operator to link both cranes together and operate them simultaneously with one single button push, ideal for handling of long pieces of materials.


Special anchors to attach the crane’s steel runway beam to the wooden building haunches.

Results

Crane-Tec delivered a system that exceeds the customer’s expectation and allows them to easily and safely move products throughout their amazing facility.

 